October 22, 2026
Province Provides Update on Provincial Trunk Highway 10 Stoney Creek Bridge Closure and Repairs
Manitoba Transportation and Infrastructure is providing an update on the Provincial Trunk Highway 10 bridge closure over Stoney Creek near Ethelbert. The bridge remains closed following significant damage caused by heavy rainfall and flooding in late June and early July.
Detailed engineering assessments confirmed the existing structure is beyond repair and will need to be replaced.
Construction of a temporary detour in the immediate vicinity of the bridge site is complete and open to traffic. The detour will provide an interim route while a permanent replacement structure is designed and constructed.
Work is underway to complete detailed design and obtain regulatory approvals for the new structure. Construction of the replacement structure is anticipated to begin in winter 2026-27 with an estimated completion date in fall 2027.
Motorists are encouraged to check current road conditions at https://manitoba511.ca/ before travelling.